Virtual tour of new Acute Mental Health Unit

This virtual tour shows progress as of June 2024. 

September - December 2024

Key to the design of our new facility is to provide a home-like environment, and to make use of natural light with windows, glass, indoor courtyards and skylights.These elements can now be seen as the building work progresses.

Cladding on the exterior, and a pop of colour. The brick and timber cladding give a residential effect.

Cladding on the exterior, and a pop of colour. The brick and timber cladding give a residential effect

View of external courtyard

View of external courtyard

Bedrooms have a view outside

Bedrooms have a view outside

Skylights used throughout. Height and light make for a spacious feel

Skylights used throughout, height and light make for a spacious feel

May - August 2024

Construction continues and by the end of August much of external scaffolding has been removed.

Internal fitout underway. Brickwork, together with timber cladding, a key part of the design

Internal fitout underway. Brickwork, together with timber cladding, a key part of the design

The plant room in the ceiling continues to take shape. Minister Doocey and Suze Redmayne, MP for Rangitikei view progress

The plant room in the ceiling continues to take shape

Jan - May 2024 - Construction continues, roof completed

The new building is taking shape and work continues on the external cladding, the roof, and the interior structure.

Work on the internal structure underway

Work on the internal structure underway

A view from above, roof nearing completion

A view from above, roof nearing completion

Window installation

Window installation

September - December 2023 - Framing and construction

Framing and construction of the building began in September, and the large structural frames were in place by the end of the year. The design vision for the roof takes its inspiration from the nearby mountain ranges of the Tararuas and the Ruahines – made of high wooden interior ceilings to reflect the influence of the landscape.

Framing erected and underway

Framing erected and underway

Roofing and bracing well underway. Corrugated, colour steel roofing for stage 1 is installed

Roofing and bracing well underway. Corrugated, colour steel roofing for stage 1 is installed

February - August 2023 - Foundations completed

The foundation for our new Acute Mental Health Unit was completed on 23 August 2023, and took six months in total.

LT McGuinness now on site and enabling works. First major concrete pour occuring for stage 1 exterior foundation

LT McGuinness now on site and enabling works. First major concrete pour occuring for stage 1 exterior foundation

First section of stage 1 foundation completed. Third pour for stage 2 commences

First section of stage 1 foundation completed. Third pour for stage 2 commences

Concrete foundations completed

Concrete foundations completed

August 2022 - January 2023 - Construction site cleared

Ahead of the construction crew commencing work, the building site was cleared of buildings and trees.  Pullar Cottage (previously used for doctors’ accommodation) was removed as a result of poor condition ruling out relocation. However, thanks to a deconstruction approach its lovely matai flooring, doors and window frames were able to be re-purposed. In addition to the surrounding trees that were required for removal, a plan for transferral was done in partnership with Pae Ora and local iwi. Many were transferred to other areas of the campus, while the large Totara tree was given to Rangitāne to be used for carvings that will form part of the new facility.

Prior to removal, deconstruction and the last of Pullar Cottage

Prior to removal, deconstruction and the last of Pullar Cottage

Site being cleared for new Acute Mental Health Unit, before ground works begin

Site being cleared for new Acute Mental Health Unit, before ground works begin

February 2020 - September 2023 - The beginning, turning a concept into a detailed design

In February 2020 a concept design was developed. Government approval for the business case was received in September 2020. By March 2021, architects were appointed, and work on te preliminary design got underway. Preparations for developed design then began in October 2021. In June 2022 a cultural narrative was put in place to support the detailed design. This was Te Wao-nui-a-Tane, which translates as “The Great Forest of Tane” It reflects the ecosystem of integrated health. By September 2022 the detailed design was completed and procurement of a main contractor got underway.

Start of a concept design, preliminary design workshop for AMHU launches, and design shared with Heretaunga residents

Start of a concept design, preliminary design workshop for AMHU launches, and design shared with Heretaunga residents

AMHU entry design impression, Northern road view and street view

AMHU entry design impression, Northern road view and street view

AMHU aerial view, detailed design and cultural narrative in place to support the detailed design

AMHU aerial view, detailed design and cultural narrative in place to support the detailed design

The establishment of a new purpose-built Acute Mental Health facility is well underway. Construction commenced in February 2023 and by August the foundation was complete. By December, the large structural beams were in place and roofing has begun. The forecast completion date is June 2025, and the budget $66.6 million.

The new unit will have 28 beds, and is 2,900 m2 in size. Looking to the future, there is provision for four to eight beds to be added. The building was design was inspired by the nearby mountain ranges - the Tararuas and the Ruahines. It will be welcoming, warm and make good use of natural light to enhance the therapeutic nature of care.

Contact us

For any enquiries of feedback relating to the Acute Mental Health Unit Project, you can contact us on +64 6 350 8967 or email ourplace@midcentraldhb.govt.nz

For media enquiries, contact us at hnzmedia@tewhatuora.govt.nz