A look at the Outpatient Building site

75% primary steel is now up, and the team are starting to infill with secondary steel for the windows and the roof. The white recyclable wrapping is in place for weather protection whilst the fire rated paint is applied. There are about 120 workers on site each day and the focus for the next few months is the paint application, preparing for the façade installation and pouring of the concrete floors. 

Some great new images of the Outpatient Building site from Trev Hill Photography.

Geeves Scaffold Workers double clipped to the progressive scaffold build. 

Geeves Scaffold Workers double clipped to the progressive scaffold build. 

The wrap provides a weather controlled environment, which allows the steelwork to be painted with consistency and less overspray/spray drift.

The wrap provides a weather controlled environment, which allows the steelwork to be painted with consistency and less overspray/spray drift.

Geeves scaffold workers progressing north side scaffold build.

Geeves scaffold workers progressing north side scaffold build.

Dart Engineering welder with equipment on a load-out platform coordinates with the main crane to allow working on different floor levels.

Dart Engineering welder with equipment on a load-out platform coordinates with the main crane to allow working on different floor levels.

Level 4 plant room west. Steel rigging crew use an elevated work platform to access the bolted primary steel roof joints.

Level 4 plant room west. Steel rigging crew use an elevated work platform to access the bolted primary steel roof joints.

A worker fixes timber to control a set-down area on the main floor prior to the floor being poured with concrete.

A worker fixes timber to control a set-down area on the main floor prior to the floor being poured with concrete.

A John Jones Steel Rigger, tightening the primary steel connections from an elevated work platform.

A John Jones Steel Rigger, tightening the primary steel connections from an elevated work platform.

A John Jones steel rigger, tightening the primary steel connections from an elevated work platform.

A John Jones steel rigger, tightening the primary steel connections from an elevated work platform.

The southwest corner of the Outpatient Building site facing towards the Inpatient Building site.

The southwest corner of the Outpatient Building site facing towards the Inpatient Building site.