Health Capital Envelope (HCE) funded projects in the Define, Design and Delivery Project Phases as at September 2023 Download PDF Version
Northern Region
Region-wide
Region-wide
ID# |
Project Name |
Project Stage |
Description |
10227 |
Replacement of end-of-life network devices, Northern Region |
Design |
Replacement of 826 end-of-life network devices. |
Te Tai Tokerau
Te Tai Tokerau
ID# |
Project Name |
Project Stage |
Description |
10023 |
Bay of Islands Hospital Redevelopment, Phase 2 |
Deliver |
Phase 2 of the rebuild of the hospital, incorporating a primary care clinic, outpatient space and shared reception. |
10047 |
Te Kotuku Redevelopment, Whangārei Hospital |
Deliver |
Addressing capacity constraints and provide relief until the new hospital is commissioned, including: Special Care Baby Unit, Acute Assessment Unit, Ambulatory Care/Outpatients and Laboratory |
10068 |
Regional IT System Platform Implementation, Northern Region |
Deliver |
Implement a new regional platform to support an integrated network of primary, community and hospital-based care. |
10230 |
Project Pihi Kaha - Whangārei Hospital Redevelopment |
Design |
Replacement of a large section of the main hospital block to address building issues and increase capacity |
102116 |
Radiation Oncology Project, Whangārei Hospital |
Design |
New radiation oncology facility and redevelopment of the Jim Carney Cancer Centre |
30025 |
Manaia House - Community Mental Health - Whangārei |
Deliver |
Purchase and fit-out of a building in Whangārei to co-locate and integrate community-based mental health and addiction services. |
30026 |
Kaitaia Hospital Weathertightness Remediation |
Design |
Weatherproofing to extend building lifespan. |
Waitematā
Waitematā
ID# | Project Name | Project Stage | Description |
10036 | Construction of new building, Tōtara Haumaru North Shore Hospital | Deliver | Increasing capacity across the Northern region with a new build comprising eight surgical theatres, an endoscopy suite with four procedure rooms, five 30-bed wards for post-surgical care and to support acute and elective inpatient bed requirements, and associated clinical support services. |
10049 | Waitematā Infrastructure Services Remediation Programme - Tranche 1A | Deliver | Mitigation of risks in relation to critical assets and building resilience, focused on demolition of facilities, and relocation and provision of new infrastructure at the North Shore Hospital campus to support Tōtara Haumaru. |
10050 | E Tū Wairua Hinengaro - Forensic Psychiatric Services Facilities Replacement, Mason Clinic, Auckland | Deliver | Replacement of four units and 60 inpatient beds at the Mason Clinic in Auckland (includes Tranches 1A and 1B). |
10204 | Manaaki Hōhonu - Construction of inpatient ward and ICU, Waitākere Hospital | Design | Increasing capacity at Waitākere Hospital with a new build comprising a 30-bed inpatient ward and an 8-bed ICU (with 6 ICU beds initially fitted out), with future-proofing for additional clinical space. |
10222 | Building For The Future - Fit-out of shelled theatres, inpatient wards and procedure rooms, Tōtara Haumaru, North Shore Hospital. | Deliver | Increasing capacity in Northern region with the fit-out of four surgical theatres, one 30-bed ward and two endoscopy procedure rooms within Tōtara Haumaru. |
10238 | Construction of Waitākere Primary Birthing Unit | Design | Construction of a 970sqm primary birthing facility, which includes six birthing/postnatal suites, to meet the urgent demand for maternity services in the West Auckland area. |
10241 | Electrical Infrastructure Upgrade, Waitākere Hospital | Design | Upgrade to critical elements of electrical infrastructure at Waitākere Hospital |
10247 | Waitematā Infrastructure Services Remediation Programme - Tranche 1B | Design | Programme of remediation projects of critical plant and equipment to ensure compliance with relevant standards and legislation, and projects enabling and supporting campus resilience. |
30040 | North Shore Hospital Central Sterile Services Department Upgrade | Deliver | Upgrade (including the installation of an instrument tracking system) to service the entire North Shore campus, including Tōtara Haumaru, and provide backup for Waitākere theatres |
Te Toka Tumai Auckland
Te Toka Tumai Auckland
District |
ID# |
Project Name |
Project Stage |
Description |
Te Toka Tumai Auckland |
10001 |
Facilities Infrastructure Remediation Programme - Tranche 1, Auckland City Hospital and Greenlane Clinical Centre |
Deliver |
Remediation of urgent infrastructure at Auckland City Hospital and Greenlane Clinical Centre |
Te Toka Tumai Auckland |
10056 |
Facilities Infrastructure Remediation Programme - Tranche 2, Auckland City Hospital and Greenlane Clinical Centre |
Deliver |
Building Resilience - New central plant, tunnels and future integration at Auckland City Hospital and Greenlane |
Te Toka Tumai Auckland |
10069 |
Tū Pono Āroha - Patient Administration System (PAS) Upgrade and Integration, Northern region |
Deliver |
Delivery of a replacement Patient Administration System (PAS) for Auckland to secure business continuity and integrate with other current Northern Region PAS solutions |
Te Toka Tumai Auckland |
102115 |
Linear Accelerators Replacement, Auckland City Hospital |
Deliver |
Linear Accelerator cancer radiation machines |
Te Toka Tumai Auckland |
30002 |
Starship Paediatric Intensive Care Unit (PICU) Bed Expansion and Atrium Redevelopment |
Deliver |
Expansion of PICU to create an additional 10 beds in the current non-clinical area, and the development of atrium and public spaces on levels two and three in Starship Hospital to accommodate new public spaces, medical day stay and displaced PICU staff. |
Counties Manukau
Counties Manukau
ID# |
Project Name |
Project Stage |
Description |
10015 |
Scott Building (Clinical Block) Recladding, Middlemore Hospital |
Deliver |
Recladding of Scott Building (Clinical Block) |
10045 |
Acute Radiology Unit Relocation, Middlemore Hospital |
Deliver |
Relocate existing radiology department from earthquake-prone Galbraith Building to Harley Gray Building. |
10059 |
Core Infrastructure Upgrade, Middlemore Hospital |
Design |
Phased upgrade of essential infrastructure at Middlemore Hospital, e.g., power, lifts, air-conditioning, medical gases, water, etc. |
10209 |
Manukau Superclinic expansion and planned care capacity increase, Manukau Health Park |
Deliver |
Critical expansion of capacity at Manukau Health Park with supporting infrastructure, including outpatients, theatres, renal, radiology, integrated breast care and more. |
10210 |
Building Recladding, Middlemore Hospital & Manukau Health Park |
Deliver |
Year 2 of Stage 2 of the recladding programme to address leaky building and cladding issues. |
10225 |
New Specialised Rehabilitation Centre, Manukau Health Park |
Design |
Relocation of the Auckland Regional Spinal Unit from Counties Manukau’s Ōtara campus at Middlemore Hospital to a new purpose built facility. |
Te Manawa Taki
Hauora a Toi Bay of Plenty
Hauora a Toi Bay of Plenty
ID# |
Project Name |
Project Stage |
Description |
10252 |
Seismic Strengthening, Tauranga Hospital |
Design |
Structural upgrade of building to protect post-disaster level services (includes relocation of kitchen). |
30003 |
Te Whare Maiangiangi - Mental Health Acute Inpatient Unit Upgrade, Tauranga Hospital. |
Design |
Refurbishment project adding 3 additional beds through two wing extensions and life safety upgrades. |
Waikato
Waikato
ID# |
Project Name |
Project Stage |
Description |
10073 |
Te Pae Tawhiti - Acute Mental Health Inpatient and Renal Facilities Replacement, Waikato Hospital. |
Design |
New builds to replace the existing mental health and renal facilities at Waikato hospital (Tranche 1 works) |
102119 |
Linear Accelerator Replacement, Waiora Campus, Waikato Hospital |
Deliver |
Replacement of Linac cancer radiation machine and to access updated Linac technology. |
30048 |
Emergency Department Upgrade, Tokoroa Hospital. |
Deliver |
Upgrade of the Emergency Department at Tokoroa Hospital. |
Tairāwhiti
Tairāwhiti
ID# |
Project Name |
Project Stage |
Description |
10207 |
Te Whare Awhiora - Mental Health Inpatient Facility Replacement, Gisborne Hospital |
Deliver |
New build to replace the existing facility and increase capacity at Gisborne Hospital. |
10223 |
Electrical System Upgrade, Gisborne Hospital |
Design |
Electrical upgrade, including supply to site and replacement of ageing generators. |
10258 |
Electrical Infrastructure Upgrade, Gisborne Hospital |
Design |
Strategic business case in development. |
30032 |
New Child and Youth Health Community Hub, Gisborne Hospital |
Design |
Centralised location for a one-stop-shop providing services for children and youth. |
Taranaki
Taranaki
ID# |
Project Name |
Project Stage |
Description |
10079 |
Project Maunga - Taranaki Base Hospital Redevelopment - Stage 2 |
Deliver |
Second stage of a 3-stage inpatient building programme. Construction of a new building housing core clinical services including ED, radiology, laboratory, maternity services, neonatal and ICU (incorporating High Dependency Unit). |
102117 |
Replacement Linear Accelerator and Integrated Cancer Care Centre, Taranaki Base Hospital |
Design |
Replacement of LINAC cancer radiation machines. |
30033 |
Tukapa House and Te Puna Waiora: Acute Mental Health Inpatient Facility Upgrades, Taranaki Base Hospital. |
Design |
Safety upgrades for the existing facility (Te Puna Waiora) and a new build 4-bed intensive rehabilitation unit at Taranaki Base Hospital (Tukapa House) |
Lakes
Lakes
ID# |
Project Name |
Project Stage |
Description |
10075 |
Mauri Ora - Mental Health and Addictions Inpatient Facility Replacement, Rotorua Hospital. |
Design |
Replacement and capacity expansion of current mental health facility with two additional beds on completion and four more available in the future. |
30017 |
Woman, Child and Family Facility Upgrade, Rotorua Hospital |
Deliver |
Upgrade of Woman, Child and Family Facilities to meet health and safety standards. |
Central
Whanganui
Whanganui
ID# |
Project Name |
Project Stage |
Description |
30044 |
Infusion Therapy Unit Construction, Whanganui Hospital |
Design |
New build of a local outpatient chemotherapy unit and Infusion Therapy Unit development. |
30045 |
Waimarino Health Centre Extension, Whanganui |
Design |
Health Centre redevelopment to co-locate primary and community services. |
Capital, Coast and Hutt Valley
Capital, Coast and Hutt Valley
ID# |
Project Name |
Project Stage |
Description |
10226 |
Electrical System Upgrade, Wellington Total Energy Centre |
Design |
Electrical upgrade, including supply to site and replacement of ageing generators. |
10240 |
Elevator Renewal, Wellington Hospital |
Deliver |
Renewal of lifts in seven buildings across Wellington Regional Hospital. |
10255 |
Infrastructure Remediation Works - Tranche 2, Wellington Regional Hospital |
Define |
Lifts, copper pipes, seismic and other remediation. Further work required to scope some remaining remediation elements. |
10256 |
Front of Whare and Emergency Department Refurbishment, Wellington Regional Hospital |
Design |
Remediation of seismic, configuration and capacity issues. |
30008 |
Infrastructure Remediation Works (copper pipe replacement) - Tranche 1, Wellington Regional Hospital |
Deliver |
Replacement of hot-water pipes. |
30015 |
Te Whare Ahuru - Acute Mental Health Inpatient Facility Replacement, Hutt Hospital. |
Deliver |
New build to replace the existing facility and increase capacity at Hutt Hospital. |
30016 |
Special Care Baby Unit and Maternity Facilities Upgrade, Hutt Hospital |
Deliver |
Facility redevelopment to improve care and outcomes for hapu mama, pepe and whanau. |
Wairarapa
Wairarapa
ID# |
Project Name |
Project Stage |
Description |
30037 |
Wairarapa Hospital Outpatients Refurbishment |
Design |
Refitting of the outpatients’ area for a triaging area, new office and clinic space. |
Te Matau a Māui Hawke's Bay
Te Matau a Māui Hawke's Bay
ID# |
Project Name |
Project Stage |
Description |
10148 |
Seismic Remediation Works, Hawke’s Bay Hospital |
Deliver |
Seismic strengthening remediation works on theatres, and acute assessment unit. |
10208 |
Radiology Facilities Redevelopment, Hawke’s Bay Hospital |
Design |
Refurbishment of Radiology Buildings. |
10218 |
Surgical Services Expansion Project (SSEP), Hawke’s Bay Hospital |
Deliver |
Bringing the previously shelled theatre eight online, expanding the post anesthesia care unit (PACU), and minor modifications to the central sterile services department (CSSD). |
102118 |
Linear Accelerator & Bunker Installation, Hawke's Bay Hospital |
Design |
Installation of linear accelerator machine and construction of bunker to expand regional cancer services. |
30013 |
Procedure Rooms Upgrade, Hawke’s Bay Hospital |
Deliver |
Fitout of two procedure rooms in the Ruakopito (Endoscopy) building to enable ophthalmological procedures to be undertaken whilst maintaining endoscopy procedures. |
30014 |
Main Electrical Supply Upgrade, Hawke’s Bay Hospital |
Deliver |
Replacement of the district’s main electrical switchboards in hospital buildings. |
Te Pae Hauora o Ruahine o Tararua MidCentral
Te Pae Hauora o Ruahine o Tararua MidCentral
ID# |
Project Name |
Project Stage |
Description |
10020 |
Acute Mental Health Inpatient Facility Replacement, Palmerston North Hospital. |
Deliver |
New construction of an Acute Adult Mental Health facility currently on the main campus. |
10257 |
Critical Infrastructure Interim Works, Palmerston North Hospital |
Design |
Installation of new substation and replacement of existing substation and essential services. |
30019 |
Surgical, Procedural, Interventional, Recovery Unit Expansion, Palmerston North Hospital |
Deliver |
Refurbishment to increase surgical, procedural, and interventional capacity. |
Te Waipounamu
Nelson Marlborough
Nelson Marlborough
ID# |
Project Name |
Project Stage |
Description |
10243 |
Project Whakatupuranga - Nelson Hospital Redevelopment |
Define |
Design and construction of a new Acute Services Building and refurbishment of existing clinical buildings across the campus to address seismic issues and critical services infrastructure. |
30021 |
Wāhi Oranga - Acute Mental Health Inpatient Unit Upgrade, Nelson Hospital. |
Design |
Upgrades to improve safety and support improved models of care at Nelson Hospital |
30024 |
Boiler Replacement, Wairau Hospital, Blenheim |
Deliver |
Replacement of boilers with an energy efficient, sustainable option. |
Waitaha Canterbury
Waitaha Canterbury
ID# |
Project Name |
Project Stage |
Description |
10007 |
Waipapa Tower 3 construction, Christchurch Hospital Redevelopment |
Deliver |
Addition of a new ward tower to the existing Waipapa Building (formerly Acute Services Building) to cater for 160 bed spaces across five wards. |
10220 |
Compliance Works, Christchurch Hospital and Christchurch Women’s Hospital |
Deliver |
Structural strengthening, passive fire compliance works, structural upgrades. |
10232 |
Hillmorton Hospital Redevelopment - Tranche 1, Christchurch |
Design |
Construction of a new acute mental health facility and supporting infrastructure for the redevelopment of the Hillmorton campus. |
10246 |
Endoscopy Unit Expansion, Christchurch Hospital |
Design |
Fit-out of four new procedure rooms, construction of two new procedure rooms, and the refurbishment of two existing procedure rooms |
30006 |
Parkside Building Refurbishment, Christchurch Hospital |
Deliver |
Remediation of facility issues, including refurbishment of wards in the Parkside Building at Christchurch Hospital. |
Te Tai o Poutini West Coast
Te Tai o Poutini West Coast
ID# |
Project Name |
Project Stage |
Description |
30041 |
Mental Health Inpatient Facility Replacement, Grey Base Hospital |
Design |
Construction of a new purpose-built facility to provide a modern, therapeutic environment. |
Southern
Southern
ID# |
Project Name |
Project Stage |
Description |
10025 |
Project Whakatuputupu - New Dunedin Hospital |
Deliver |
New Dunedin Hospital campus to replace hospital services currently provided in the Clinical Services Block and the Ward Block, and an Energy Centre. |
10026 |
Keeping The Lights On - Service Maintenance, Dunedin Hospital |
Deliver |
Essential maintenance projects to maintain services until completion of the new Dunedin Hospital development. |
10027 |
Urgent Interim Works, Dunedin Hospital |
Deliver |
Redevelopment of gastroenterology, audiology and ICU facilities, and a deferred maintenance programme |
30030 |
Rural Primary Birthing Unit Construction, Wanaka and Clyde |
Deliver |
Construction of two new birthing facilities to service expanded population in Central Otago. |